Cyprium Metals Limited (ASX:CYM) has provided a further update on the status of the refurbishment of the Nifty Copper Project in Western Australia whilst the company is progressing the finance process for the restart of the operation.
Current Status
The Nifty site has been secured and there are sufficient personnel on site to maintain the site to enable a quick transition to construction activities once finance is obtained. The personnel will ensure maintenance of statutory regulations and reporting requirements, and operational, mechanical and electrical integrity of the infrastructure, and continue to advance refurbishment activities with existing materials that are already on site.
Scrap retrieval activities are continuing, and the site team are sending equipment that is surplus to project requirements (such as underground equipment) back to Perth for sale and disposal. Sale of surplus and salvage equipment has already commenced.
Corporate and head office costs have been minimised by reducing staff and executive positions and the remainder are on a part time basis, who are focused on regulatory and reporting requirements, and advancing the Nifty restart finance process.
“The Nifty Copper Project is in a state of readiness so that at the completion of the finance process, there is an effective and efficient transition from care and maintenance to full construction and then commissioning to production,” Managing Director Barry Cahill said.
“The Nifty Copper Project restart is the first phase of a potential +20-year life and remains robust, with current Australian dollar copper pricing at a similar level to what was used in the Restart Study, which was completed in March 2022. The increase in resources and the reduction in base costs, such as freight, since the study was finalised will only improve that robustness.
We look forward to commencing construction post finance, then producing and shipping copper metal, not ore or concentrate, but LME Grade A copper metal cathode, in the north of Western Australia.”
Nifty Copper Project Status
The acquisition transaction for the Paterson Copper Assets, including Nifty Copper Project (on care and maintenance), was completed at the end of March 2021.
Upon transaction completion, personnel and drill rigs were immediately mobilised to site to commence work for the compilation of the Nifty Restart Study (completed and released to the market on 11 March 2022) and to conduct environmental surveys to commence the approval process (the first approval was lodged 14 November 2021) for the restart of the Nifty copper project.
}The progress made by Nifty employees to date has been exceptional, with significant progress towards being operationally ready. The workforce again is commended for their efforts and progress whilst the site has remaining on care and maintenance since its acquisition. This has also been achieved at Nifty over the past ~450 days (over 300,000 hours worked) without a Lost Time Injury.
Project Finance Update
The financing process remains the key focus for Cyprium. The financing process, which is targeting A$240 million to A$260 million debt funding package (including cost overrun contingency and working capital) for the financing of the Nifty restart and project costs, expected to comprise senior secured financing, subordinated debt, and offtake financing. Positive discussions, due diligence activities, documentation, and negotiation of terms with numerous parties are continuing.