Euro Manganese Inc. (ASX/TSXV: EMN) has confirmed it has produced high-purity electrolytic manganese metal (HPEMM) from its Demonstration Plant at the Chvaletice Project the Czech Republic.
An external laboratory has confirmed the first HPEMM sent for testing has met the Demonstration Plant target specifications and was at 99.9% Mn metal purity. High-purity manganese sulphate (HPMSM) is now under production in the final module and will be sent for external laboratory testing in due course.
The Demonstration Plant is anticipated to commence acceptance testing in late April. Upon successful completion of acceptance testing, the Company will commence deliveries of Plant HPEMM and/or HPMSM to customers. Customer deliveries of the company’s Demonstration Plant products is not expected to be required for completion of offtake contracts.
Detail on Plant Commissioning
• Commissioning of the process flowsheet commenced in November 2022 on a module-by-module basis.
• The Ore-to-Slurry and Magnetic Separation modules were commissioned prior to the end of 2022 and successfully produced a manganese concentrate from the Chvaletice manganese carbonate tailings.
• Commissioning of the Leaching and Purification module commenced in January 2023 and successfully produced a purified solution.
• This solution, and both products from the subsequent steps (HPEMM and HPMSM), are required to be sent to an external laboratory that has the specialised measurement equipment required for analysis of the low-level of impurities targeted in the Demonstration Plant process. External laboratory turnaround times are currently 3-4 weeks, which has caused a slight delay in the commissioning schedule.
• External laboratory results from the Leaching and Purification module were received in February 2023, confirming the purified solution met the required specification.
• The Electrowinning module successfully produced selenium-free HPEMM flakes in March 2023. This metal was sent to an external laboratory for testing, which has confirmed this metal was produced at 99.9% Mn purity and at the design specification of the Demonstration Plant.
• The final Dissolution and Crystallization module has now commenced commissioning and HPMSM will be sent to the external laboratory for testing in due course. The Company will provide an update once on-spec HPMSM is produced.
• Representatives from the company which manufactured the Demonstration Plant are expected to arrive on site in late April and the plant will undergo acceptance testing. This will involve running the Plant on a module-by-module basis to confirm each module meets the design specification of product quality, throughput, and reagent consumption.
For further information please visit: https://www.mn25.ca/