20,000 TPA In Additional Production Targeted For Argentinian Project
Caucharí-Olaroz Lithium Project partners project partners Lithium Americas Corp. (TSX: LAC) and Ganfeng Lithium Co. Ltd have approved the commencement of development planning for a second stage (Stage 2) expansion in Argentina.
The Stage 2 expansion is targeting at least an additional 20,000 tonnes per annum (tpa) of lithium carbonate equivalent (LCE) production capacity from Caucharí-Olaroz.
“Caucharí-Olaroz is on track to become the largest new lithium brine operation in over 20 years,” commented George Ireland, Chairman of Lithium Americas.
“With construction for Stage 1 expected to be complete within the next year, together with Ganfeng Lithium, we are beginning to plan our next phase of growth in Argentina.”
The Caucharí-Olaroz Stage 2 expansion is targeting the following development parameters:
- Production capacity of at least 20,000 tpa LCE to commence in 2025.
- Construction commencing in H2 2022, following the commissioning and start-up of the initial 40,000 tpa operation (Stage 1).
- Infrastructure additions to support long-term expansions beyond Stage 2.
The Caucharí-Olaroz Partners expect to provide further details of the Stage 2 expansion plan by Q4 2021, followed by an updated feasibility study in 2022.
Stage 1 Construction Update
Construction on the initial 40,000 tpa Stage 1 operation remains on track for first production in mid-2022.
- There are currently over 1,000 workers on site, following the completion of additional camp capacity to ensure compliance with strict COVID-19 health and safety protocols. No positive cases of COVID-19 have been reported at site in eight months.
- In Q2 2021, senior members of Ganfeng Lithium’s commissioning and construction team arrived in Argentina to assist the project through to start-up. Ganfeng Lithium’s team brings recent experience constructing and commissioning lithium carbonate plants in China.
- All major equipment and the majority of bulk materials have been delivered to site, reducing risk of supply chain delays.
- The evaporation ponds are well advanced with sufficient brine inventory to support production ramp up.
- Mechanical construction of the lime plant is completed and the piping work to connect the lime line is more than 95% complete.