Commences Procurement For ATO Gold Mine Growth In Mongolia
Steppe Gold (TSXV:STGO) has commenced procurement of major capital items for the Phase 2 fresh rock expansion, targeting annual production of 150,000 oz Au Eq, at the 100%-owned ATO Gold Mine in Monglia
President and CEO, Bataa Tumur-Ochir, said the first major purchase is a new crushing plant.
“We are very pleased to kick start the capital procurement programme for our Stage 2 fresh rock expansion at the ATO Gold Mine,” Mr Tumur-Ochir said.
“We have prioritised the expansion of crushing capacity as it will also significantly accelerate stacking rates at the heap leach phase of the project and this is expected to support increased gold production in late 2021 and 2022.
“We have also started design work to expand the camp capacity and plans are advancing for value added power solutions.
“With a strong balance sheet and encouraging demand from lenders we expect to accelerate capital works on our Phase 2 expansion through the second half of 2021 as we target fresh rock production of 150,000 oz Au Eq starting in 2023.”
The new crusher will have a crushing capacity of 1,000t/hr, more than three times the current crusher capacity, and it will fully support planned mining rates for the fresh rock phase where we have estimated throughput rates of 2-2.5m t.p.a.
Construction of foundations and installation of the new crusher will start in early April and it is scheduled to be operational by July 2021. The new crushing unit comprises two primary jaw crushers and a cone crushing circuit.
Sourced from a leading international supplier, the crushing plant will cost around US$5 million in total, inclusive of civil construction work, installation and testing. The crushing plant purchase is being partly financed by a US$2.9 million loan from a leading Mongolian commercial bank.
In conjunction with the start of procurement of long lead items, Steppe Gold continues discussions with Mongolian and international lenders on a multi-tranche project debt facility to finance the Phase 2 expansion, expected to include a grinding circuit, a leach/CIP plant, and a flotation circuit.
Mr Tumur-Ochir said metallurgical testing is progressing well with encouraging results and the bankable feasibility study is on track for completion in summer 2021.